Wednesday, July 17, 2013

Initial catch up!

7/3/2013 Broke ground! Just moved topsoil and leveled






7/8/2013 Dug hole for foundation
7/9/2013 laid out footings and poured them



7/10/2013  poured walls--- Cherry valley concrete did the work


7/11/2013  removed forms from walls, installed egress windows.  Noticed they had left a spot for a side door, which was suppose to be out the back. Emailed tom about this.

7/12/2013 Did the basement plumbing in the floor, floor not poured yet.
7/15/2031 Put black tar on foundation.  Larry called to schedule meeting on 7-17 at 8am.  Discussed waterproofing, he has no paperwork showing we paid for basement waterproofing.  Found our papers were missing page 6, which included all the basement and big ticket items!!  Emailed everyone at AE about this asking for Tom to get corrected.  Met the neighbor to the south, Lee.  Nice retired guy.  Sounds like he is watching them build, says they are doing a good job.  He has been there since 12-16-09, and is very happy with it.  He did say to take a notebook everyday and write down items that are not right, after you take possession.  He said you have 365 days to get any issues to AE to get fixed, but only if they have them in writing.  Some of his things he complained about they fixed after 3 years.  

No comments:

Post a Comment